Overview
The Lakeport facility operates under a license issued by the Federal Energy Regulatory Commission (FERC). Lakeport Hydroelectric One, LLC (a subsidiary of Eagle Creek Renewable Energy) is the licensee for the facility. The facility's current license was issued in 1983 and expires in 2023. On August 31, 2018, the licensee filed documents with the FERC (available below) to initiate the relicensing of the project using the Traditional Licensing Process (TLP).
Documents
All filings related to the relicensing process are available from the FERC's eLibrary website: elibrary.ferc.gov. Search for filings by project number: P-6440. The licensee is making available its major document submissions and major FERC orders on this website:
Initial filing on August 31, 2018:
- NOI, request to use TLP, and PAD (172 pages; 12.55 MB)
Joint Meeting/Site Visit Schedule on December 19, 2018:
- Notice of Joint Meeting and Site Visit filed 12/4/18 (8 pages; 861 kB)
- Lakeport Joint Agency Meeting Presentation on 12/19/2018 (32 pages; 1.52 MB)
Draft License Application filing on January 29, 2021:
- Draft License Application (364 pages; 39.9 MB)
Final License Application filing on August 30, 2021:
- Final License Application (514 pages; 23.5 MB)
Lakeport Hydroelectric One, LLC will also provide hard copies of any of the above documents upon request. A reproduction cost fee of $0.25/page will apply to such requests. Please use the link below to download a request form and mail the completed form, along with a check for the reproduction cost fee, to Lakeport Hydroelectric One, LLC, care of Eagle Creek Renewable Energy, to request a hard copy of any document.
The licensee will continue to post public information regarding the relicensing of the Lakeport facility as the process continues.